Construction Project Timeline
Generate a visual schedule of your construction site with estimated durations
Project parameters
50 m2500 m2
Estimated total duration
9 - 15 months
Villa G+1 — 150 m2 — Casablanca
Construction Schedule
PhaseScale: 0 - 15 months
Building Permit
1.5 - 2.5 months
M0 - M3
Earthwork & Foundations
1.0 - 1.5 months
M2 - M4
Structural Work
3.0 - 5.0 months
M3 - M9
Secondary Work
2.0 - 3.0 months
M6 - M12
Finishes
1.5 - 2.5 months
M8 - M15
Phase Details
1
Building Permit
Duration : 1.5 - 2.5 months | M0 to M3
File submission, review, obtaining permit via Rokhas.ma
- Architect plans validated by the Order
- File submission Rokhas.ma / municipality
- Technical committee review
- Obtaining building permit
2
Earthwork & Foundations
Duration : 1.0 - 1.5 months | M2 to M4
Excavation, footings, ground beams, slab
- Site layout by surveyor
- Earthwork and excavation
- Footing formwork and reinforcement
- Foundation concrete pouring
- Backfill and compaction
3
Structural Work
Duration : 3.0 - 5.0 months | M3 to M9
Wall construction, columns, beams, slabs, staircase, roofing
- Load-bearing walls and partitions
- Column and beam formwork
- Slab reinforcement and pouring
- Concrete staircase (if multi-story)
- Roofing and parapets
4
Secondary Work
Duration : 2.0 - 3.0 months | M6 to M12
Electrical, plumbing, joinery, insulation, waterproofing
- Electrical installation
- Plumbing (supply and drainage)
- Aluminum/PVC joinery
- Terrace waterproofing
- Thermal insulation (RTCM)
5
Finishes
Duration : 1.5 - 2.5 months | M8 to M15
Tiling, painting, sanitary, kitchen, fixtures
- Floor and wall tiling
- Interior/exterior paint
- Sanitary installation
- Fitted kitchen installation
- End-of-site cleaning