Construction Project Timeline

Generate a visual schedule of your construction site with estimated durations

Project parameters

50 m2500 m2
Estimated total duration
9 - 15 months
Villa G+1150 m2 — Casablanca

Construction Schedule

PhaseScale: 0 - 15 months
Building Permit
1.5 - 2.5 months
M0 - M3
Earthwork & Foundations
1.0 - 1.5 months
M2 - M4
Structural Work
3.0 - 5.0 months
M3 - M9
Secondary Work
2.0 - 3.0 months
M6 - M12
Finishes
1.5 - 2.5 months
M8 - M15

Phase Details

1

Building Permit

Duration : 1.5 - 2.5 months | M0 to M3

File submission, review, obtaining permit via Rokhas.ma

  • Architect plans validated by the Order
  • File submission Rokhas.ma / municipality
  • Technical committee review
  • Obtaining building permit
2

Earthwork & Foundations

Duration : 1.0 - 1.5 months | M2 to M4

Excavation, footings, ground beams, slab

  • Site layout by surveyor
  • Earthwork and excavation
  • Footing formwork and reinforcement
  • Foundation concrete pouring
  • Backfill and compaction
3

Structural Work

Duration : 3.0 - 5.0 months | M3 to M9

Wall construction, columns, beams, slabs, staircase, roofing

  • Load-bearing walls and partitions
  • Column and beam formwork
  • Slab reinforcement and pouring
  • Concrete staircase (if multi-story)
  • Roofing and parapets
4

Secondary Work

Duration : 2.0 - 3.0 months | M6 to M12

Electrical, plumbing, joinery, insulation, waterproofing

  • Electrical installation
  • Plumbing (supply and drainage)
  • Aluminum/PVC joinery
  • Terrace waterproofing
  • Thermal insulation (RTCM)
5

Finishes

Duration : 1.5 - 2.5 months | M8 to M15

Tiling, painting, sanitary, kitchen, fixtures

  • Floor and wall tiling
  • Interior/exterior paint
  • Sanitary installation
  • Fitted kitchen installation
  • End-of-site cleaning