Casablanca1.5 - 2 monthsRokhas.ma functional, optimized process
Rabat1.5 - 2.5 monthsRokhas.ma active, good flow
Kenitra1.5 - 2 monthsResponsive municipality
Marrakech2 - 3 monthsHigh volume, variable delays
Tangier2 - 3 monthsStrong urban growth
Fes2 - 3 monthsHistoric zones take longer
Agadir2 - 3 monthsGood functioning
Meknes2 - 2.5 monthsModerate volume
Oujda2.5 - 4 monthsSlower administration
Rural3 - 4+ monthsLess frequent committees
These delays are indicative and assume a complete and compliant file. An incomplete file may double the delay. Protected areas require additional reviews.
Frequently Asked Questions
How much does a building permit cost in Morocco?
Filing fees are set by municipal decréé and range from 500 to 5,000 MAD depending on surface and municipality. The most significant costs are architect fees (5-8% of total cost) and BET (1-3% of structural work).
Can I build without a permit?
No. All construction in Morocco requires a building permit (Law 12-90). Building without a permit exposes you to fines, démolition, and criminal prosecution.
How long is a building permit valid?
The permit is valid for 2 years from issuance. Work must begin within this period. Construction must be completed within 5 years.
What is Rokhas.ma?
Rokhas.ma is the national platform for digitizing urban planning permits in Morocco. It allows online submission and tracking of applications.
What to do if the permit is refused?
In case of refusal, the municipality must justify its decision in writing. You can modify your plans and resubmit. An appeal to the wali or administrative court is possible.